Our Projects

Discover how Sterling Ridge builds, powers, and connects communities across our diverse portfolio of projects.

FEATURED PROJECTS

NextStar Battery Plant

Client: A-BM

$23.5 Million Combined | 2023

Executed shallow foundations and associated civil site work for the state-of-the-art LG/Stellantis NextStar Battery Plant in Windsor, Ontario. Contract scope encompassed foundational and civil packages for both the $17 Million Cell Building and the $6.5 Million Modular Building, alongside supporting site structures.

Parkway ATMS Upgrades

Client: DBI Services Inc. & Windsor-Essex Mobility Group

2021

Installed high-density polyethylene (HDPE) conduit via directional boring for Advanced Transportation Management System (ATMS) fiber optic rings and power cables. The project included installing two specialized 80-foot high-mast concrete poles along E.C. Row Westbound at Huron Church Road and Malden Road to support critical CCTV camera upgrades.

Scully/St. Marks Pump Station & Shoreline Protection

Client: Town of Tecumseh

$19.2 Million | 2023–Present

A collaborative construction project delivering a new stormwater pump station, outlet, and robust shoreline protection walls. Scope includes the total reconstruction of storm and sanitary sewers, watermains, roadway, and street lighting along Riverside Drive, alongside the decommissioning of two existing pump stations.

South Middle Road Feeder Ducts Project

Client: Hydro One Networks Inc.

$70 Million Joint Venture

Sterling Ridge Infrastructure Inc. and EPTCON Ltd. executed the Engineering, Procurement, and Construction (EPC) for the South Middle Feeder Ducts Project to support growing power demand in the Leamington area. The scope involved constructing a concrete-encased underground duct system to route 24 electrical feeders south from the South Middle Transformer Station to Mersea Road 11. In total, the project delivered approximately 52 km of duct bank utilizing over 1.5 million feet of conduit, reinforced rebar, and more than 20,000 m³ of concrete. Work also included backfill, splice vault installation, cable pulling, terminations, splicing, and testing/commissioning.

Traffic Signal Infrastructure Upgrades

Client: DBI Services Inc. & Windsor-Essex Mobility Group

2020

Utilized specialized horizontal directional drilling (HDD) across the Herb Gray Parkway to install traffic signalization infrastructure upgrades on behalf of the Ministry of Transportation (MTO).

WDBA – Transmission Line Relocation

Client: Valard LP

$27 Million | 2017–2018

Relocated 230kV and 115kV Hydro One overhead transmission lines underground to facilitate the construction of the Gordie Howe International Bridge Canadian Point of Entry. Scope featured 23 100-foot-deep caisson foundations founded on bedrock, shallow termination foundations, engineered sheet piling, 36-inch HDPE directional drilling, open-cut and grouted duct banks, the excavation and disposal of over 30,000 cubic meters of soil, and the implementation of a strict environmental management plan.