ARDC New Battery Technology Centre

Client: Stellantis

$21 Million | 2023–2025

Constructed a new addition to the existing Stellantis ARDC Research Centre. The expansion featured its own dedicated 27,600-volt electrical feeder supplied by the local utility provider to ensure independent, reliable power distribution for the facility's advanced testing equipment.

BNA – Concrete Works (Gordie Howe International Bridge)

Client: Bridging North America

$32 Million | 2020–2023

Executed the Engineering Fill and Surcharge Package for the Gordie Howe International Bridge, which involved supplying and installing over 750,000 metric tonnes of aggregate material and more than 850,000 metric tonnes within the site. Scope also included the installation of instrumentation devices to monitor ground settlement and groundwater pressure. Sterling Ridge maintained an intensive 12-hour, six-day workweek, delivering full production efficiency ahead of critical deadlines.

Dominion Blvd Rehabilitation

Client: Windsor-Essex Solid Waste Authority

$5.5 Million | 2023

Delivered the comprehensive reconstruction of Dominion Boulevard from Northwood Street to Ojibway Street. Scope featured the full rehabilitation of the roadway pavement, storm sewers, watermains, and street lighting infrastructure.

Engineering Fill & Surcharge Project (Gordie Howe International Bridge)

Client: Bridging North America

$34 Million | 2019–2023

Executed the Engineering Fill and Surcharge Package for the Gordie Howe International Bridge, which involved supplying and installing over 750,000 metric tonnes of aggregate material and more than 850,000 metric tonnes within the site. Scope also included the installation of instrumentation devices to monitor ground settlement and groundwater pressure. Sterling Ridge maintained an intensive 12-hour, six-day workweek, delivering full production efficiency ahead of critical deadlines.

EWSWA Regional Landfill (Cell 5 North)

Client: Windsor-Essex Solid Waste Authority

$11.7 Million | 2024–2025

Executed mass excavation and construction of Cell 5 North at the EWSWA Regional Landfill. Work included comprehensive site preparation, earthworks, and liner system installation for environmental protection. The scope involved grading, subgrade prep, and placement of engineered protective layers for long-term operational support. Additionally, drainage infrastructure and leachate collection was integrated to improve environmental safeguards.

Ford Oakville Assembly Plant

Client: Ford Motor Company

$15.8 Million | 2022

Replacing all conveyors that deliver the new electric vehicle throughout the plant to different tooling for assembly.